Plenty Road Stage 2 contract awarded

15 April, 2019Plenty Road Upgrade


The $178.6 million Plenty Road Upgrade is another step closer to completion, with the contract for the next stage of works between Bush Boulevard and Bridge Inn Road awarded to Decmil.

This upgrade will improve traffic flow and access to jobs, schools, shops and parks for the 35,000 people who use this road each day.

The upgrade includes:

  • widening the road from 4 to 6 lanes between Bush Boulevard and Riverdale Boulevard
  • widening the road from 2 to 4 lanes between Riverdale Boulevard and Bridge Inn Road
  • improving cycling and walking facilities
  • upgrading 12 intersections, including Bridge Inn Road, Waterview Drive and Francesca Drive.

This work is separate from the works recently conducted by a private developer.

Major construction on Stage 2 of the Plenty Road Upgrade will begin later this year and the project is expected to be complete by mid-2021.

Stage 1 of the Plenty Road Upgrade between McKimmies Road and Bush Boulevard is nearing completion and is on track to be complete in mid-2019.

For more information visit the Plenty Road Upgrade page.