During Stage 1 of the upgrade, we:

  • added a new lane in each direction between McKimmies Road and Bush Boulevard
  • upgraded 5 intersections, including Childs Road and Centenary Drive
  • installed traffic lights at Rivergum and Mayfield Drives
  • widened the existing footpath and create a new shared walking and cycling path
  • built on-road cyclist lanes
  • installed 10,000 metres of safety barriers.

Works started in March 2018 and were completed in mid-2019.Plenty Road Stage1 map

View a larger version of the Plenty Road Upgrade Stage 1 map (PDF, 175.0 KB).

Construction partner

Our construction contractor for Stage 1 was DECMIL.